|
WWTP Odor Control Modifications Prime Contractor
6/8/2009
When our long term client had more projects to bid than available estimators, they turned to us to provide the added estimating capacity.
Power Plant Expansion Prime Contractor
5/7/2009
Our client called with an urgent need to have all of the power plant piping estimated on the project.
Data Center Feasibility Estimate Data Center Con
5/5/2009
A regular client needed a budget for a data center expansion project in a short period of time.
Detention Center General Contractor
4/24/2009
The project involved an extensive amount of earthwork on the site.
Medical Center Electrical Upgrade Electrical Con
4/24/2009
Our client received a bid package for an extensive scope on renovating and upgrading the electrical systems at a medical center.
Data Center Feasibility Estimate Data Center Con
4/21/2009
The data center consultant on the project needed a budget in a short period of time for a new data center project.
Extra Work Claim Electrical Contractor
4/20/2009
Our client received a bid package that specified a project completion date that was missed by three months.
Museum Feasibility/Conceptual Estimates - Architec
4/1/2009
Our client was engaged to develop a concept on a new museum project. The studies included several configurations and options.
Hospitality Retail Store Prototype Consulting Fi
2/5/2009
Tempest Company teamed up with a retail consulting firm as a part of an overall evaluation of a newly configured store prototype.
Educational Academy Electrical Contractor
2/5/2009
The bids for a new school were requested with a very short bidding period.
Operations Center Sitework Contractor
2/5/2009
Three days before the bid Tempest Company was contacted to see if the site earthwork could be taken off on what turned out to be a large earthwork package.
Data Center Development Firm
2/5/2009
The developer of a Data Center needed a detailed cost estimate for the budget estimate on a proposed data center for one of their clients.
Apartment Complex Electrical Contractor
1/12/2009
An electrical contractor client of Tempest Company needed the entire electrical scope of work estimated in order to bid the project.
Corporate Headquarters Building Construction Ma
1/6/2009
One of our construction management clients was required to have an independent estimate of the costs for the concrete scope of work on the project.
Specialty Winery Owner
1/6/2009
A new client of Tempest Company needed the costs estimated for defective electrical work to resolve a dispute with the electrical contractor.
Hospital Addition Mechanical Contractor
1/6/2009
A short bidding period on the project created a problem for one of our mechanical contractor clients.
Conceptual Studies Architect
1/6/2009
An architect turned to Tempest Company in order to determine the conceptual costs within a complicated Work Breakdown Structure (WBS).
Hospital Construction Program Hospital Owner
1/6/2009
A hospital owner was in the process of undertaking a major expansion of their facilities.
Big Box National Retail Store Electrical Contrac
11/19/2008
A new client for Tempest Company wanted to bid on the electrical scope of a national retail chains new big box facility.
Hospital - Electrical Contractor
11/17/2008
A regular electrical contractor client of ours had us prepare the electrical takeoff and estimate on the project.
Building Cost Studies University
11/15/2008
A University needed to examine the cost of an adaptive re-use for an older building versus the construction of a new building.
Cost Studies National Retailing Firm
11/6/2008
A large national retailing company wanted a confirmation of the potential cost variances between the exterior building envelope materials.
Market Penetration Study International Material
10/9/2008
A prominent material supplier wanted to determine the size of the market for selected products, in a very short time period, for the construction industry.
Emergency Generator Study Electric Utility
8/25/2008
In determining the feasibility of a project the electric utility engineering group needed to know the costs to located and support either a 2500 or 400 kw emergency generator unit.
Performing Arts Addition University
8/25/2008
A budget was need for project approval to proceed on an addition for a performing arts center project.
Motel Prototype International Motel Firm
8/11/2008
In a continuation of a previous estimating assignment, the prototype configuration of a proposed motel was revised with another estimate being requested by the owner.
Town Border Station Natural Gas Transmission Com
8/8/2008
A pipeline company needed a cost estimate for a town border station on a pipeline expansion project.
Fire Line Electric Utility
8/8/2008
An electric utility company wanted to expand a fire line at one of their sites.
Fire Department Headquarters General Contractor
8/8/2008
A general contractor wanted to bid a design assist project without using subcontractors on the project.
Various commercial Projects Stucco & Plastering
8/8/2008
The contractor needed assistance bidding several projects in a short amount of time.
Street Repair Schedule Paving/Civil Works Contra
8/8/2008
The contractor bid the major reconstruction of a street based upon the traffic being re-routed so all lanes we available at one time.
High Rise Condominium Project - Caulking & Sealing
7/8/2008
A high rise condominium project was bidding, along with a dozen other smaller projects.
Water Discharge Line Electric Utility
7/8/2008
An electric utility company is in the process of upgrading the facility.
Law Enforcement Center Construction Manager
7/8/2008
A construction management firm recently obtained a contract for a new law enforcement center.
Fresh Food Distribution Warehousing Electrical C
7/8/2008
An electrical contractor was asked by their long standing client to provide a conceptual design build estimate on the electrical systems of a distribution warehouse complex.
Manufacturing Facility Mechanical Contractor
7/8/2008
A mechanical contractor needed to bid a manufacturing plant.
Process Piping Scope Evaluation Manufacturing Ow
7/8/2008
A process piping contractor was terminated on a project.
|